top of page

Local Business News: Drainage Project Works

The City of Truth or Consequences will start the MSD Roadway and Drainage Improvements project.

This will impact a few businesses in the Downtown area, so we want to help share this news to help you plan accordingly.


Please see the map and written schedule below. Work starts from 7/10/23 and will end 12/1/23.


MAP


SCHEDULE


Project Schedule: 7/10-8/16 — Phase 1

Affected Areas: Mcadoo St from Foch St to Jones St


Scope: Mcadoo St. will undergo a complete street reconstruction from Foch St to Jones St.

Please use alternate routes during this time frame.


Project Schedule: 8/16 - 10/1— Phase 2

Affected Areas: Daniel St from Broadway St to Mcadoo St


Scope: Daniel St. will undergo a complete street reconstruction from Broadway St to Mcadoo St.

Please use alternate routes during this time frame.


Project Schedule: 10/1 — 12/1— Phase 3

Affected Areas: Mcadoo St from Jones St to Pershing and Pershing from Broadway to Main Ave


Scope: Mcadoo St. and Pershing St will undergo a complete street reconstruction from Main Ave to Broadway St.

Please use alternate routes during this time frame.

59 views
bottom of page